As part of the NT Government’s Berrimah Area Plan, the Department of Infrastructure, Planning and Logistics is constructing a new intersection on Amy Johnson Avenue and a new industrial connector road, Flightpath Road, which will provide a vital access point to the Berrimah North land development. The new intersection with Amy Johnson Avenue will be located approximately 800 metres north of the Stuart Highway.

Snapshot

Cost - $6.2 million
Project commencement - June 2019
Estimated completion - December 2019

Map

flightpath road extent of road works map

Contact

Project Director: Geoff Thomas
Phone: 0428 620 294
Email: geoffrey.thomas@nt.gov.au